Project Highlights The I-35W/Crosstown Commons Area is heavily congested, has high crash rates and requires weaving between lanes. After several years of design setbacks due to unacceptable traffic closure periods, the Minnesota DOT pursued precast segmental alternatives in order to minimize erection times and traffic closures. Closures for major movements during construction are estimated to be no longer than two months. |
|
|
Our Role McNary Bergeron & Associates is providing construction engineering services, including integrated segment shop drawings, construction analysis, step-by-step erection procedures, falsework design, and geometry control. |
|
|
Construction Method and Specifications
|
|
|
Owner Minnesota Department of Transportation |
Contractor Ames / Lunda / Schafer (Joint Venture) |
|
Total Contract Value $288 million |
Timeline June 2007 to November 2009 |
|
Project Website |
|
|