 |
|
|
Past Projects |
|
|

Woodrow Wilson Memorial Bridge
Washington, D.C.
Work on the project began in 2000
and is
scheduled for completion in 2008 |
Woodrow Wilson Memorial Bridge
Located in Washington, D.C. is a
6,000-foot long replacement structure for the original Woodrow
Wilson Memorial Bridge.
The twin replacement structures feature
deck widths of up to 148 feet utilizing a unique structural system
that mimics the arch bridge at other points along the Potomac River.
The concrete v-shaped piers are designed
to be built using the pre-cast segmental method. There are four
steel girders which sit atop each V-Pier and support a reinforced
concrete deck. The 175-foot navigation channel is spanned with an
eight-leaf double bascule structure. |
-
Owner:
Woodrow Wilson Memorial Bridge
Maryland Department of
Transportation
State Highway Administration
-
Contractor: Potomac Constructors,
LLC – Maryland Approach Joint Venture of Edward Kraemer & Sons,
American Bridge, & Trumbull Corp.
-
Type: Segmental Concrete V-piers.
|
-
Erection Method: Temporarily Stayed
Cantilevered V-Piers
-
Services Provided: Construction
Engineering including design of erection equipment and temporary
supports for erection of V-pier segments, lift rigging and hitch
design, integrated segment shop drawings, design of work trestle
and temporary piers and bulkheads.
|
|
|
Troup-Howell Bridge
The new Troup-Howell Bridge, a $38.7
million signature project for the New York Department of
Transportation, will be a triple-member steel arch bridge that rises
70 feet above the road surface. When complete, it will also be the
widest three-member pure arch bridge in the country. Edward Kraemer
& Sons, Inc. is constructing the main span over the Genesee River
and the 7 approach spans as a replacement to the original
cantilevered multi-girders structures built in 1953. The structure
upgrades an important transportation link in the city of Rochester
in addition to dramatically changing the city skyline.
The new structure follows the same alignment as the existing bridge.
Traffic will be diverted to half of the existing structure while the
other half is demolished and the new structural steel is
constructed. This involves erecting two of the three arch ribs on a
series of temporary props, installing hanger strands and floor
beams, and casting a concrete deck. Once complete, traffic will be
diverted to the new arch structure and the remaining existing
structure demolished. The third arch can then be erected and
remaining floor beams and concrete deck completed. |

Troup-Howell Bridge
Genesee River, New York State
Work on the project began in 2004
and is
scheduled for completion in June 2007. |
-
Owner: New York State Department of
Transportation
-
Contractor: Edward Kraemer & Sons,
Inc.
-
Type: Three-member Steel Arch
-
Erection Method: Incremental
erection on temporary props
-
Length: 433’ main span
|
-
Width: 130’ wide
-
Span Data: 433’ main span over the
Genesee River,
7 approach spans with average span length of 100’
-
Services Provided: Construction
Engineering including analysis of the structure during
construction, girder erection procedures, existing structure
demolition procedures, and design of erection equipment and
temporary supports.
|
|
|

Maumee River Bridge
Toledo, Ohio
Work on the project is
scheduled
for completion in June 2006. |
Maumee River Bridge
At a construction cost of $220 million
dollars, the I-280 Maumee River Crossing is the largest single
construction project in ODOT history.
When completed in late 2006, this
cable-stayed, precast segmental Signature bridge will carry six
lanes of Interstate 280 across the Maumee River in Toledo, and will
replace the Craig Memorial Bridge, one of the few remaining
lift-span bridges which remains on the U.S. interstate system.
Fru-Con Construction Corporation, of
Ballwin, Missouri, is ODOTs contractor for this project |
-
Owner: Ohio Department of
Transportation (ODOT
-
Contractor: Frucon Construction
Corporation
-
Type: Precast segmental approaches
and cable-stayed main span
-
Construction Method: Approaches –
span by-span using overhead truss
|
-
Main Span – cable stayed cantilever
using deck mounted hoist.
-
Square Footage: 1,2000,000 square
feet
Width: 114’
-
Span Data: 150’ typical approaches,
612’ main span
-
Services Provided: Oversight for
ODOT reviewing Contractor’s procedures and equipment.
|
|
|
Route 123 Over Occoquan River
Archer Western Contractors began
construction the twin, 360m bridges over the Occoquan River in 2003.
Each bridge includes a conventional precast bulb-t approach
structure.
The main span is constructed using
spliced, post-tensioned bulb-t girders. As such, all of the girders
are erected on temporary falsework and post-tensioned together to be
self-supporting. |

Route 123 Over Occoquan River
Occoquan, Virginia
Work on the project
began in 2003
and is
scheduled for completion in June 2007.
|
-
Owner: Virginia Department of
Transportation
-
Contractor: Archer Western
Contractors, Ltd.
-
Type: Spliced, Post-tensioned Bulb-T
-
Length: 360m (1181’)
|
-
Width: 37.65m (123’-6”)
-
Span Data: 73m (239’-6”) Main Span
-
Services Provided: Girder Erection
Analysis, Falsework Design, Erection Equipment, Substructure
Redesign
|
|
Additional
Past
Projects |
|
|
|
|
Home |
Services |
Background |
Projects |
Offices |
Contact Us |
News |
|
|
Copyright © 2005-2008 McNary Bergeron & Associates, LLC
Engineered Construction ® is a Registered Trademark
of McNary Bergeron & Associates, LLC |
|