 |
|
|
Additional Past Projects |
|
|

US6 over Pawnee Creek
Logan County, Colorado
Work on the project began in 2004
and is
scheduled for completion in 2005 |
US6 over Pawnee Creek
The Pawnee Creek Bridge is typical of
many highway bridges throughout the country. The precast box beam
structure is being constructed in two stages to replace existing
structures.
Duckels Construction began this project
in the fall of 2004. When completed in 2005, the new bridge will
provide increased capacity and greater width to accommodate future
demand.
In 2004, the Colorado Department of
Transportation began requiring “Girder Erection Plan” submittals for
all new construction. This specification aims to protect the
traveling public and enhance the safety of the construction process.
McNary Bergeron provided the Girder
Erection Plan for Duckels construction. This plan outlined the crane
information, rigging, and girder stabilization required to place the
girders. In addition to providing assurance to the owner that
erection would be conducted in a safe manner, these services also
add a measure of efficiency, which benefits the whole construction
team.
|
-
Owner: Colorado Department of
Transportation
-
Contractor: Duckels Construction,
Inc.
-
Type: Precast prestressed box beam
with CIP concrete composite deck
-
Length: 217’
|
-
Width: 89’
-
Span Data: Two (2) 107ft spans
-
Services Provided: Girder Erection
Plan and Analysis, Onsite support and supervision
|
|
|
Sikorsky Bridge
Balfour Beatty Construction is
completing the $80 million replacement of the 1939 Sikorsky Bridge,
which carries 80,000 vehicles per day on Connecticut Route 15 over
the Housatonic River in Milford/Stratford, Connecticut.
Work on the project consists of
demolition of the existing Sikorsky Bridge, a four-lane structure
with a metal grid deck and metal barrier, and replacement of it with
a five-span continuous plate girder structure with composite
concrete deck. The new structure, consisting of an Eastbound and
Westbound bridge, has six lanes, full shoulders and a sidewalk. Upon
completion of the Eastbound bridge, traffic will be diverted to the
new span, the existing bridge will be demolished, and the Westbound
bridge will be constructed.
The bridge consists of steel plate girders varying in depth from 11’
to 16’. Field sections are each approximately 100’ long and erected
from land based and barge mounted cranes. Erection of girders is a
challenging operation due to the extremely steep terrain at either
abutment, strong tides in the river, and an active commuter rail
line immediately adjacent to the East abutment.
|
Girders are shipped by rail from the
fabrication facility in Oregon to the jobsite. From there, they are
loaded onto barges and floated into position in anticipation of the
erection process. After all girders are erected, temporary forms are
installed and the concrete deck poured to make a composite
structure.

Sikorsky Bridge
Housatonic River, Milford/Stratford, Connecticut
Work on the project
began in 2001
and is
scheduled for completion in June 2005 |
-
Owner: Connecticut Department of
Transportation
-
Contractor: Balfour Beatty
Construction
-
Type: Reinforced Deck on Steel Plate
Girders
-
Erection Method: Land and water
based cranes on temporary erection bents
-
Length: 1,800’
|
-
Width: Eastbound Structure – 60’
wide
-
Width: Westbound Structure – 70’
wide
-
Span Data: 5 spans, averaging 360’
long
-
Services Provided: Construction
Engineering including analysis of the structure during
construction, girder erection procedures, and design of erection
equipment and temporary supports.
|
|
|

Skyway Bridge
Oakland, California
Work on the project is
scheduled
for completion in June 2006. |
SFOBB “Skyway” Bridge
The Skyway portion of the Oakland Bay
Bridge Replacement consists of dual precast segmental structures
measuring 2,103 meters in length with a width of 2x26 meters. This
structure is unique in its size and complexity.
Each structure includes four frames
connected with internal hinge beams having typical span lengths of
160 meters. Typical segments are 8 meters long and up to 800 tons in
weight. These segments are erected in balanced cantilever.
In special instances, segments on
opposite sides of a pier must be lifted incrementally in order to
avoid overstressing the pier columns. This degree of complexity in
construction requires a significant amount of engineering by the
contractor.
McNary Bergeron is providing Engineering
oversight and equipment design for the Kiewit Flatiron Manson Joint
Venture.
|
-
Owner: Caltrans
-
Contractor: KFM (Kiewit, Flatiron,
Manson) a Joint Venture
-
Type: Precast Segmental - Balanced
Cantilever
-
Length: 2103m
|
-
Width: 2x26m
-
Span Data: 13 cantilevers, 160m
typical span
-
Services Provided: Engineering
oversight & equipment design
|
|
|
Susquehanna River
The Kraemer-Wagman Joint Venture team
entered a winning bid of The $82.4 million to build the twin,
5,900-foot-long structures over the Susquehanna river on the
Pennsylvania Turnpike. The new segmental concrete box girder bridges
will be the first of their kind built in Pennsylvania. Each bridge
will be 57 feet wide and have a total of 40 spans, each span
averaging 150 feet. The spans will be built using the span-by-span
method with an underslung truss.
The old bridge will remain open as the
new one is being built, minimizing any impact to the flow of
Turnpike traffic over the river. Once traffic is rerouted over the
new structure, the old bridge will be disassembled. |

Susquehanna River Bridge
Pennsylvania
Work on the project
began in 2004
and is
scheduled for completion in May 2007.
|
-
Owner: Pennsylvania Turnpike
Authority
-
Contractor: Kraemer-Wagman Joint
Venture
-
Type: Precast Segmental
-
Erection Method: Span-by-span with
underslung truss
-
Length: 5,900 ‘
|
-
Width: Dual Boxes, Each 57’ wide
-
Span Data: 40 spans, averaging 150’ long
-
Services Provided: Construction Engineering
including Construction analysis, Shop drawings, equipment design
and on-site engineering support
|
|
Return To Current Projects |
|
|
|
|
Home |
Services |
Background |
Projects |
Offices |
Contact Us |
News |
|
|
Copyright © 2005-2008 McNary Bergeron & Associates, LLC
Engineered Construction ® is a Registered Trademark
of McNary Bergeron & Associates, LLC |
|