PROJECT HIGHLIGHTS: ROAD 22/75 BRIDGES
The Road 22/75 Bridges are part of the overall master plan for bypassing the congested downtown Haifa area via the new Carmel Tunnels.
Our Role
McNary Bergeron is providing construction engineering services including geometry control, construction analysis, and integrated shop drawing templates. We are also independently verifying several aspects of the design.
Construction Method and Specifications
-Twin 12-span bridges
-Single box precast segmental
-Balanced cantilever
-Overhead erection gantry
-50m typical span length
-11m to 14m variable deck width
Owner
Israel National Roads Company, Ltd.
Contractor
Ashtrom Engineering & Construction
Designer
YSS Consulting Engineers Ltd.
Timeline
June 2009-Mid 2010